The second phase of the redevelopment of Mandela National Stadium has entered a critical stage, with major structural works now in full progress as Uganda prepares to host the 2027 Africa Cup of Nations.

Newly released photos from stadium management show heavy construction activity around the main stands, including cranes, scaffolding and interior demolition works. The government, together with the UPDF Engineering Brigade, is carrying out the broader modernisation project valued at approximately $60 million.

The latest phase follows a CAF inspection earlier this year, after which the renovation effort shifted into a full-scale reconstruction project aimed at upgrading the stadium to meet modern continental standards ahead of AFCON 2027, which Uganda will co-host with Kenya and Tanzania.

One of the most noticeable developments is the vertical expansion of sections of the stadium. The upgraded design is expected to turn Namboole into a multi-level sports facility featuring improved VVIP and VIP lounges, executive hospitality suites, a modern media centre capable of hosting more than 100 journalists and a dedicated Venue Operations Centre.

Construction teams have also started one of the stadium’s biggest internal modifications by relocating the dressing rooms from the eastern side of the arena to the western section. The adjustment is intended to align the player tunnel with the main media and VIP zones, which is said to be among CAF’s important requirements for major tournaments.

Photos from the site also show ongoing works around the athletics track and pitch-side areas, including preparations for sand pits and installation of cables linked to upgraded floodlights, VAR systems and high-speed fibre connectivity for broadcasting purposes.

The redevelopment project is operating under strict timelines. Uganda is expected to showcase major progress during another CAF inspection scheduled for August 2026, with authorities targeting at least 50 percent completion of the structural upgrades by that time.

Officials also hope to complete the training annex and surrounding infrastructure by December 2026, before the final handover planned for January 2027 to allow enough time for testing and operational preparations ahead of the tournament kickoff in June 2027.

The “Demolition in Progress” signs visible in some sections of the stadium mainly refer to the removal of old interior structures dating back to the 1990s, especially around the VVIP areas, as contractors prepare for the new tiered design approved by the Local Organising Committee and government officials overseeing the project.